| Whole Factory | Design Studio |
| Factory Scale | ||
| Site of a Factory | : | 4100㎡ |
| Factory | : | A part of factory is made of steel. There are a three- storied building and a office. (Total floor space 880㎡) |
| Factory with Shed | : | A bigger steel construction (450㎡)/ A smaller steel construction (180㎡) |
| Material Yard | : | 850㎡ |
| Engineering Manager | |
| Building Construction Engineering Manager | Class 1 - 2 Workers/ Class 2 - 3 Workers |
| Construction Managing Engineers | Class 2 - 3 Workers |
| Weld Engineering Manager (WES8103) | Class 1 - 1 Worker/ Class 2 - 5 Workers |
| Weld Coach (WES8107) | Class 1 - 1 Worker |
| Steel Fabrication Engineering Manager | Class 1 - 2 Workers/ Class 2 - 4 Workers |
| Steel Fabrication Inspector | 3 Workers |
| Steel-frame Ultrasonic Wave Inspector | 1 Worker |
| Nondestructive Inspector (NDI-UT) | Class 1 - 2 Workers |
| High-strength Bolted Connection Manager | 4 Workers |
| Head Shipbuilder | 2 Workers |
| Design & CAD (Computer Aided Drawing) Drawing Technician | 4 Workers |
| Technical Expert | ||
| Semi Automatic Welding Engineer (JISZ3841)-(SN-2FH,SA-3FH) | 9 Workers | |
| Arc Welding Engineer (JISZ3801)-(N-2FH,A-2FH) | 9 Workers | |
| Stainless Welding Engineer (JISZ3821)-(TN-F) | 2 Workers | |
| Aluminum Welding Engineer (NK)-(T-A2F), (NK)-(S-A2F,H) | 8 Workers | |
| Iron Engineering Technician (Steel Structure) | Class 2 - 3 Workers | |
| Gyotestu (Plate Forming) Shipbuider | 2 Workers | |
| Major Facility | ||||||
| Overhead Traveling Crane (2.8 ton) | 5 | Positioner | 1 | |||
| Outside Traveling Crane (2.8 ton) | 1 | Roll-bending Machine (6mm) | 1 | |||
| Band Sawing Machine (700H) | 1 | Manual Arc Welding Machine | 9 | |||
| Guillotine Shearing Machine (13mm) | 1 | Gouging Machine | 5 | |||
| Oil Press (250 ton) | 1 | Plasma Cutting Machine | 2 | |||
| Drill Press | 6 | Supersonic Flaw Detector | 1 | |||
| CO2 Semi Automatic Welding Machine | 20 | Film Thickness Gauge | 2 | |||
| TIG Welding Machine | 2 | CAD System (2D, 3D) | 7 Sets | |||
| MIG Semi Automatic Welding Machine | 4 | Other Machines | 1 Set |
| Other | |
| Publication of patent applications | (2000-160817) Construction of double flooring with under floor wiring using FRP form. |
| An application for a patent | (2004-055048) A way of producing a new building material, which contains transparent parts. |
| Research and Development | (1998 Miyagi Creating Technology Assistant Industry ) |
| Simple approach thick small diameter pipe semi automatic welding machine. | |